News 23 Jan 2023
For our TWP blog, we thought we would start from the seabed up and find out about the considerations for cables at our two project sites off the coasts of Orkney and Aberdeen (33km and 44km offshore respectively). Answering the questions were Taco Heseding, TWP’s Engineering & Technical Lead who led our successful ScotWind bids, and Gunnar Watthé, Electrical Engineering Manager. Both have joined TWP from founder company DEME and are now supporting planning phases of the project.
Gunnar: My work in offshore wind began with cables procurement for sites off the coasts of Belgium and Germany – later, I moved more towards electrical infrastructure design. Last year, I moved into an exciting area of development for DEME, working on our hydrogen and wider portfolio of green molecule projects.
Taco: I moved into renewables after starting out in water system development, working as an engineer and project lead on a variety of projects in Africa and Europe. At DEME, my current focus is on leading bid development teams, but I previously worked with Gunnar on projects in Asia, which is where I started to get more deeply involved in the planning and implementation of cables infrastructure.
Cables are too often seen as the end of an offshore wind project, the final item on the agenda. I was lucky to get a different viewpoint while working on the DEME projects. There are countless cable design and installation possibilities coming from all over the world and this is becoming a highly exciting and complex area of development.
Taco: ‘Product’ is not really the right word here. We’re procuring a mix of technologies that will create a bespoke solution for our sites, rather than taking something off the shelf.
We are going to have to take a different approach to procurement, particularly in the context of the growing squeeze on supply for our industry. In the past, we could pick a design, go to market and weigh up the prices – that hasn’t been the case for some time now.
For a recent offshore wind project, we took the approach of going to suppliers without having a completed design. We started with a very simple flow-chart, which we built up layer by layer into a huge, integrated chart showing detailed work streams, including supply chain. That allowed us to get cable reservation agreements in place much earlier (3 to 4 years in advance of installation). This is a chart that Gunnar and I would like to hang on the wall of every project!
Gunnar: Cable failure remains a huge source of cost for offshore wind farms, but we are starting to see some far superior monitoring systems entering the market and they are being installed not just on export cables but also on inter-array cables too (to meet the needs of increasing voltages).
We are especially keen to review all offerings on the market for cable monitoring systems, from established technologies to those that are just coming onto the market. It’s particularly important for us to deepen our relationships with the universities here in Scotland, where we can get visibility of the latest ideas going into research. Where a technology offers the prospect of retrofitting, it may be relevant to us in the future, even if it is not in time for our first wave of procurement.
Taco: We are just starting our detailed bathymetry surveys, but we know that we will face issues with boulders in the heavily compacted sediment that we have here in Scotland. From Scotland down to the Yorkshire coast, we have a much more challenging seabed than you’d see to the south of England and Wales. This is a post-glacial seabed that is dense and can present a lot of rocks near the surface and unexpected obstacles when you start laying cables.
There are a few approaches we could take: we can cut through rock and lay cables within it (expensive and slow) or lay cables on the surface and then lay more stone on top. This is the least favoured option because of the environmental impacts, so we have some work to do to find a better, project-specific solution.
Gunnar: We may also see some sand waves bordering our Aberdeen site, though we would not expect them to be the size of those we have seen in other parts of the world.
Gunnar: Some sand waves are more challenging than others: if they are stable, that makes things a lot easier. When they start to move, that’s when you risk having the cables exposed or left unsupported by the seabed, a big risk factor for cable failure. We have encountered sand waves as high as 20m and 150m in length in other countries. If something like that moves significantly, you can imagine that it could have a devastating impact on the electrical infrastructure.
We do have a lot of experience in mitigating this risk though. We know where sand waves are present and the importance of undertaking regular and detailed bathymetric surveys in order to build up a morphodynamic model, which will tell you how the seabed is likely to look at different stages of a wind farm’s lifetime. You can also take mitigating steps like designing for lower burial depths with enhanced monitoring, or simply plan to spend a lot more at the beginning on very deep burial of the cable.
Press release 7 May, 2026
Read now
Press release 5 Mar, 2026
Press release 15 Dec, 2025
If you have any queries about our wind farm projects, TWP’s community engagement, careers with TWP, or anything else, please fill out our general enquiries form.
Contact us Feedback Form Feedback Form